8/8/2024: Project schedule updated

 

A City contractor will be resurfacing the portion of Bohrer Park’s asphalt path from Desellum Ave. to Brighton Drive.

Due to Tropical Storm Debby, the revised, remaining schedule is as follows:

  • Monday, August 12 - Tuesday, August 13: Finish cut outs, tie-ins (to allow for smooth transition) and place top-soil as needed along the existing trail in preparation for overlay.

  • Monday, August 18 - Thursday, August 22: Base asphalt installation at repair areas, and 2’’ overlay.

It is still hoped to have work completed prior to Montgomery County Schools reopening on August 26, 2024.